OCDE facility renovations: We’re halfway there

Building A has officially reopened. Building B is next

And just like that, the Orange County Department of Education is halfway through its facility renovations of the Kalmus campus. 

The transformational journey that began in early October 2023 is not only modernizing the department’s infrastructure but also enhancing the daily working environment for staff, creating contemporary and functional spaces tailored to meet the evolving needs of OCDE. With the completion of Building A in the books, it’s now time to focus on Building B.

In the first phase, Building A saw a host of improvements, including new furniture, filing cabinets, flooring, a fresh color scheme, kitchen upgrades, new roofing, ceiling tiles and comprehensive data infrastructure enhancements. The HVAC system also received an upgrade to improve airflow and employee comfort, along with various electrical upgrades.

These projects were completed on schedule, with Building A officially reopening on Jan. 16. Staff members, who temporarily relocated to Building D, have now returned to their refreshed workspaces, ready to continue their important work in a revitalized environment.

Dave Giordano, associate superintendent of Administrative Services, commended the exceptional efforts of the OCDE Facilities Planning, Maintenance and Operations team. 

“Their countless hours of dedication, helping staff move and creating comfortable temporary workspaces, have been essential to this project’s success,” said Giordano.

He also extended gratitude towards the Purchasing Department for their critical role in the process, overseeing everything from bidding to logistics planning and furniture orders.

Time for phase two

With phase one behind us, OCDE is now gearing up for phase two, which involves similar upgrades to Building B while its staff is temporarily housed in — you guessed it — Building D. 

Giordano says planning for the second phase began before the holiday break, with architectural plans submitted to the city and bid documents completed by early January. The formal bidding process, which kicked off on Jan. 15, will continue through the end of February. Construction is slated to begin on March 25, with a 16-week timeline extending into mid-July.

Giordano also revealed plans for a refresh of the Building D Conference Center upon the conclusion of phase two. 

“These renovations are not just about upgrading our facilities but are a testament to our commitment to providing an optimal work environment for our staff,” he said.

As we continue to witness the transformation of our Kalmus site, we want to extend our thanks to everyone for their patience and understanding during this period of change. Your support is invaluable in making OCDE a better place to work.

For any questions or concerns, please feel free to reach out to Sharon Hernandez at 714-966-4158.

You can see the time-lapse transformation of Building A from the old to the new in this video from our Media Services team.